Below is a short summary for the 2025 CalGreen code updates.These changes will be effective January 1st, 2026.

For more detail clink link below:

2025 California green building standards code - EV

One- And Two- Family Dwellings And Townhouses With Attached Private Garages

  • No changes from previous code cycle.
  • Still requires just EV Capable for each dwelling unit.

New Multifamily Dwellings, Hotels And Motels And New Residential Parking Facilities

  1. Essentially, the number of dwelling units determines the number of EV Ready.

Number of dwelling units= number of EV Ready spaces

  1. The number of EV Chargers is now 25%, but this percentage applies only to the unassigned/common use parking spaces that do not already have an EV Ready outlet.

Hotels and Motels

  • For new construction, 40% EV Ready and 25% EV Chargers. Applies to total number of parking spaces.
  • For additions or alternations of existing multifamily buildings and hotels/motels, all new or altered parking spaces shall have either EV Ready or EV charger. Unless determined infeasible by building/designer and subject to local agency approval.

Nonresidential

  • The new code breaks up the required EVCS columns into 2. Now distinguishes between “Office and Retail” and “Other than Office and Retail” and has different quantities for each.